Going Solar in Malta — Step-by-Step Guide

The definitive roadmap for Maltese homeowners to transition to clean energy, understand the current grant position, and secure long-term energy independence.

Solar panel installation on a Maltese rooftop under bright sunshine

Last updated: 22 November 2026

Avg. Cost
Get quotes
No grant currently open
Annual Savings
€600–1,000
Off your Enemalta bill
Payback Period
5–7 Years
Longer without a grant

Why Go Solar in Malta?

Malta is one of the sunniest countries in Europe, with over 300 days of sunshine per year. Installing solar panels on your roof is one of the smartest investments you can make as a Maltese homeowner. The 2026 government grant call has closed, but payback depends on your system price and how much power you use yourself, and systems last 25+ years, so solar remains a sound long-term investment.

Sun path over Malta through the yearMidday sun elevation at Malta, latitude about 36 degrees north, is roughly 78 degrees at the June solstice, 54 degrees at the equinoxes and 31 degrees at the December solstice. The sun rises in the east, crosses the southern sky and sets in the west.JUNE: ~78°EQUINOX: ~54°DECEMBER: ~31°EASTSOUTHWESTNoon elevation at about 36° N. Lower sun means longer shadows.
The sun climbs higher and stays up longer in summer, but even the December path is workable.

8 Steps to Going Solar in Malta

Follow this step-by-step process to go from initial research to generating your own clean electricity. Most homeowners complete the entire journey in 4–8 weeks.

1

Assess Your Roof

The first step is determining whether your roof is suitable for solar panels. The key factors to evaluate include:

  • Orientation: South-facing roofs are ideal in Malta, capturing the maximum sunlight throughout the day. South-east and south-west orientations also perform well, typically producing 90–95% of optimal output.
  • Shading: Check for obstructions such as neighbouring buildings, water tanks, satellite dishes, or trees that could cast shadows on your panels. Even partial shading can significantly reduce output.
  • Structural condition: Ensure your roof is in good condition and can support the weight of solar panels (approximately 12–15 kg per square metre).
  • Available area: A typical 3kWp system requires roughly 15–18 square metres of unshaded roof space.
☀

Flat vs Pitched Roofs

Malta has many flat roofs, which are actually excellent for solar. Panels can be mounted on tilted frames at the optimal angle (around 30–35 degrees) to maximise energy generation year-round. Ensure no shading from water tanks, chimneys, or neighbouring buildings between 10:00 AM and 4:00 PM.

2

Choose Your System Size

Most Maltese homes install systems between 3kWp and 6kWp. The right size depends on your electricity consumption, available roof space, and budget:

System Size Panels Needed Roof Area Annual Output Est. Cost (Before Grant)
3 kWp7–8 panels~16 m²~4,800 kWhGet quotes
4 kWp9–10 panels~21 m²~6,400 kWhGet quotes
5 kWp11–13 panels~27 m²~8,000 kWhGet quotes
6 kWp14–15 panels~32 m²~9,600 kWhGet quotes
ⓘ

Match System Size to Consumption

Check your Enemalta electricity bills to determine your annual consumption. A 3kWp system typically covers the needs of a 2–3 person household, while larger families or homes with electric water heaters may benefit from a 5–6kWp system.

3

Get Quotes from Installers

Obtain at least three quotes from licensed solar installers in Malta. When comparing quotes, look for:

  • Panel brand, model, and efficiency rating
  • Inverter type (string inverter vs micro-inverters)
  • Mounting system quality and warranty
  • Total installed price including VAT
  • Workmanship warranty (look for at least 5 years)
  • After-sales service and monitoring

Choose a REWS-registered, MCCAA-licensed installer and get at least three written quotes before committing.

4

Apply for the Government Grant

Households have been able to claim a government grant for solar PV and batteries through the Regulator for Energy and Water Services (REWS). The 2026 call opened on 20 April and has now closed: the battery options shut on 13 July and the whole call on 12 September 2026. As of 22 November 2026 the REWS website shows no new call.

  • The 2026 rates were 65% of the PV cost up to €645 per kWp (maximum €3,000), and 75% of the battery cost up to €600 per kWh (maximum €6,000)
  • The 2025 and 2026 calls each opened in the first half of the year, so watch rews.org.mt and the government incentives page. Budget 2027 was presented on 26 October 2026; press summaries say existing schemes are renewed for 2027, but the official text is unverified, so confirm with REWS
  • Without a grant, systems under 40 kWp can still sell exports to the grid under the €0.15 per kWh feed-in tariff for 20 years
  • No roof of your own? See community solar through Pannelli bla Bejt
⚠

Apply Before You Buy

If a new call opens, the application has to be made before you buy equipment or sign a contract. Installing first disqualifies you from the grant.

5

Check Permits & Grid Limits

Before installation, you will need to handle the necessary regulatory requirements:

  • Planning: Many domestic rooftop installations can go ahead without a planning permit under the development notification order (S.L. 552.08), subject to conditions such as the position of the panels and the height of any frames.
  • Grid notification: Systems up to 16 A per phase (about 3.7 kW single-phase) are notified to REWS. Larger systems need authorisation and Enemalta's no-objection. Your installer normally handles this.
  • Building regulations: Ensure your installation complies with the relevant regulations and permit requirements in Malta.
6

Installation

Once permits are in place and your grant is approved, the actual installation is quick and straightforward:

  • Duration: A typical residential installation takes just 1–2 days
  • Process: Mounting system installation, panel placement, electrical wiring, inverter setup, and system testing
  • Disruption: Minimal — you can usually remain in your home during the installation
  • Safety: Ensure your installer is MRA-licensed and follows all workplace safety regulations
7

Enemalta Grid Connection

After installation, your system needs to be connected to the national electricity grid through Enemalta:

  • Your installer submits the connection paperwork to Enemalta
  • Enemalta installs a bi-directional meter that tracks both electricity consumed from and exported to the grid
  • The connection process typically takes 2–4 weeks after application
  • Once connected, excess electricity you export earns the feed-in tariff if you have registered for it
8

Start Saving

With your system connected and generating electricity, you immediately begin saving on your energy bills:

  • Self-consumption: Electricity you generate and use directly saves you the full retail electricity rate
  • Feed-in tariff: Excess electricity exported to the grid earns €0.15 per kWh for 20 years on systems under 40 kWp installed without a grant
  • Monitoring: Use your inverter's app or monitoring portal to track daily production and savings
  • Annual savings: A typical 3kWp system saves €600–1,000 per year, depending on consumption patterns and self-consumption ratio
🌱

Maximise Your Savings

Run energy-intensive appliances (washing machine, dishwasher, water heater) during peak sunshine hours (10am–3pm) to maximise self-consumption and reduce reliance on grid electricity.

Solar panels covering the sunny slope of a pitched brick house roof
A south-facing roof slope filled with panels.Photo: Hannah Clover · CC BY-SA 4.0 · Source

Solar Costs & Savings in Malta

Understanding the financial aspects of going solar helps you plan your investment. Here is a detailed breakdown of what to expect:

Upfront Investment

System prices vary by panel quality and installer, and we found no official Malta price series, so get several quotes. While the 2026 grant was open it covered 65% of the PV cost up to €645 per kWp, which took roughly €1,900 off a 3kWp system. No grant is open as of 22 November 2026, so budget for the full price unless a new call is announced.

Annual Returns

Your annual saving depends on system size, how much you use yourself and the electricity price. Savings increase as electricity prices rise, making solar an effective hedge against future energy cost inflation.

Long-Term Value

Payback depends on your system price and self-consumption. With a system lifespan of 25–30 years, the years after payback are essentially free electricity.

Before you ask for quotes, work out a size and the likely savings with the solar savings calculator, then take the installer quote checklist to each installer.

Sizing logicStart from annual electricity use in kilowatt-hours on your bill, divide by the yearly output of one kilowatt of panels, and the result is the array size in kilowatts peak.ANNUAL USEkWh on the bill÷YIELDkWh per kWp=ARRAY SIZEkWpThen check roof area, shading, inverter size and battery
Sizing starts from your annual use and the yield of one kilowatt of panels.

Start Your Solar Journey Today

Don't let high energy bills dictate your lifestyle. Malta's sun is a free asset — harness it with the right step-by-step guidance.