This premium domain is available — enquire about acquiring PVMalta.com

On-Grid DIY Systems

A grid-connected system is the right choice for almost every Maltese home — but the law reserves the grid connection and certification for a warranted electrician. Here is exactly where the line sits.

Grid-tied solar inverter and consumer unit in a Maltese home

Last updated: 22 November 2026

For almost every Maltese home, a grid-connected system is the sensible default. The grid does the job an expensive battery would otherwise have to do, the feed-in tariff pays you for what you export, and the most generous grants are reserved for grid-tied systems. The catch is that Maltese law draws a firm line down the middle of the job — and the connection itself sits on the wrong side of it for a DIYer.

Why on-grid is the default in Malta

Off-grid living has a certain romance, but it makes you buy a large battery bank simply to get through the night, and then a generator for the cloudy week when it runs flat. On-grid turns that on its head. The Enemalta grid is reliable, so it becomes your storage of last resort: you export surplus generation by day and draw back what you need after dark, without paying for a single extra kilowatt-hour of battery to do it.

On top of that, Malta pays you for exports through a guaranteed feed-in tariff, and the country's grant schemes — administered by REWS through the one-stop-shop — are aimed squarely at new grid-connected systems, with the largest sums going to hybrid inverters and battery storage. The economics point one way for a typical household.

Feed-in tariff (under 40 kWp)
15c
per kWh exported, guaranteed for 20 years
Domestic grant
Closed
2026 call shut on 12 September 2026
Tariff term
20 yrs
confirm allocation terms with REWS
⚡

Don't oversize a grid-tied array

Because exports are paid at the feed-in rate rather than your import price, there is little point in building a huge array purely to sell power back. Size it to your own consumption, and if you want to bank the daytime surplus for the evening peak, add a battery rather than more panels. Our components & sizing guide walks through the numbers for a Maltese home.

Grid-tied system chainSolar panels feed a DC isolator and an inverter. The inverter output passes an AC isolator to the consumer unit and the Enemalta bi-directional meter connected to the grid.PANELSDC stringsDC ISOLATORswitch offINVERTERDC to ACAC ISOLATORswitch offCONSUMER UNIThome circuitsMETERbi-directionalTo the grid
The usual chain in a grid-tied system, from the panels to the Enemalta meter.

The legal reality: where the DIY line sits

This is the part that surprises people. You can legally do a great deal of the work yourself — but you cannot lawfully self-certify or self-connect a grid-tied system in Malta. Under the Electrical Installations Regulations (S.L. 545.24), only a holder of Authorisation A or B, or a warranted electrical engineer, may certify the installation, and Regulation 12 reserves that certification to those authorised persons. Regulation 14 then requires a completion and commissioning certificate signed by that authorised provider before the system may be energised. Impersonating an authorised provider is an offence carrying penalties.

What you may do yourself

  • Survey the roof and plan the layout
  • Size the array, inverter and battery
  • Fit the mounting frames and ballast
  • Mount and clamp the panels
  • DC-side string wiring — a grey area, and only under your certifier's terms (see below)

What a warranted electrician must do & certify

  • The AC connection to the installation
  • The consumer-unit tie-in
  • RCD protection and earthing/bonding
  • The completion and commissioning certificate (Reg. 12 & 14)
  • Sign-off that the inverter meets the grid code
⚠

No certificate, no connection

Enemalta will not change your meter or commission the system without that completion certificate. A build that no authorised person will sign off simply cannot be lawfully connected — which means it earns you neither the feed-in tariff nor any grant, because it never goes live. And be realistic here: many certifiers are reluctant to put their name to work they did not carry out themselves. Settle who will certify before you buy anything. See our regulations & permits page for the full legal picture.

A suburban house with a pitched roof partly covered by a solar array
A roof array on a pitched roof.Photo: Gray Watson · CC BY-SA 3.0 · Source

The Enemalta and REWS process, step by step

Once you know who is certifying the job, the connection itself follows a defined path. For a normal domestic system the paperwork is lighter than most people fear.

1

Get written REWS approval first

Before anything is connected, you need written approval from REWS, applied for through the one-stop-shop portal. This is mandatory, not a formality — the connection is only lawful once it is in hand.

2

Submit the Enemalta PV application

Alongside the REWS approval, you complete Enemalta's application form for a grid-connected renewable-energy system, declaring the array size and the inverter you intend to use.

3

A grid-connection study — usually not needed

A grid-connection study (a “No Objection” assessment) is only required above 16 A per phase (3.68 kW single-phase) without Volt-VAR control, or 20 A per phase (4.6 kW) with it. A typical domestic system of 3–6 kWp sits comfortably below that threshold, so most households never trigger it — and even where a study is required, check with Enemalta whether it is charged.

4

Use a compliant inverter

Your inverter must comply with the EN 50549-1 grid code, which includes mandatory anti-islanding protection. Uncertified or non-compliant kit will not pass approval, so confirm the inverter is on the approved list before you order. Our inverter guide covers the choices.

5

Enemalta fits the meter and commissions

Finally, Enemalta installs a bidirectional import/export smart meter that records the energy you draw and the energy you send back, and commissions the system. From this point your exports are metered and the feed-in tariff begins.

Approval pathwaySeven stages from survey to switch on: site assessment, planning check, grant application if a call is open, Enemalta grid application, installation, inspection and meter, then registration and commissioning.1Site assessment2Planning check3Grant call (if open)4Enemalta application5Installation6Inspection + meter7Register + commissionOrder can vary with the roof, the permit and the call
The approval path for a typical home system, from survey to commissioning.

Feed-in tariff and the grant — an honest trade-off

The feed-in tariff is guaranteed for 20 years and paid on exported units (up to 1,600 kWh per kWp per year per the REWS FIT table; confirm against your allocation letter). The 2026 rate for systems under 40 kWp that take no grant is 15c/kWh. Taking a grant has historically meant a lower rate, and under the 2026 terms a PV system with a grant cannot hold an active feed-in tariff allocation, so check with REWS. That trade-off is why the choice deserves honest thought rather than a reflex grab at the subsidy. The 2026 grant call closed on 12 September 2026 and no new call has been announced, so for now the tariff is the only support on offer.

For a DIYer, the decision is largely made for you. The grant requires a registered installer, registered equipment and a warranted-engineer commissioning certificate, so a self-built, self-imported system may not qualify; confirm with REWS. The feed-in tariff, by contrast, is open to any lawfully connected system — but “lawfully connected” still depends on that warranted-engineer certificate. So the outcome splits three ways:

Your routeGrantFeed-in tariffCertification
Pure DIY, no professional sign-offNoneNone — cannot be connectedNot possible; Enemalta won't commission
DIY build, warranted electrician certifies the AC sideNone (no registered installer)15c/kWh, 20 yearsWarranted electrician / Authorisation A or B
Full registered installerOnly when a call is open (2026 call closed)Rate depends on whether a grant was taken; 15c/kWh without oneRegistered installer + warranted engineer

In short, a certified DIY build keeps the 15c tariff but forgoes any grant, while a full professional install keeps you eligible when a grant call is open. The 2026 grant rates and closing dates are on our government incentives page.

Remember: plain grid-tie goes dark in a power cut

The same anti-islanding law that keeps linesmen safe also means a standard grid-tie inverter shuts down the moment the grid fails — even in bright sunshine. It is designed not to back-feed a “dead” line. So if you want your panels to keep the lights on during an outage, a plain grid-tie inverter will not do it.

🛡

For backup power, go hybrid

You need a hybrid inverter, a battery and an EPS (backup) output to island a protected circuit when the grid drops. This is also the combination the grant schemes reward most generously, so it is worth costing out even if outages are rare. See our battery storage and inverter guides.

The hybrid-DIY workflow that actually works

Done in the right order, a hybrid-DIY project is entirely realistic. The single most important move is to line up your certifier before you commit to anything else.

  1. Plan and size the system using PVGIS and your own consumption — see components & sizing.
  2. Line up your warranted certifier first — and a registered installer as well if you want to keep the grant on the table. Agree exactly which parts they will build, which parts you may do, and on what terms they will certify the DC side.
  3. Source EN 50549-compliant, CE-marked kit from a reputable supplier.
  4. Confirm structure and planning — rooftop PV is usually permit-exempt, but flat Maltese roofs and gregale wind loading demand engineered mounting.
  5. Mount the array yourself, and do the DC-side wiring only under your certifier's terms.
  6. Engage the warranted electrician for the AC connection, the consumer-unit tie-in and the commissioning certificate.
  7. Complete the Enemalta and REWS application, get the bidirectional meter fitted, and claim the grant if the work was professionally installed.
⚠

If nobody will certify your DIY work, use a full installer

Be honest with yourself about this. If you cannot find a warranted electrician or Authorisation A/B holder willing to certify the parts you built, the system cannot be connected — and a half-finished array on the roof helps no one. In that case the right answer is a full installer, who also keeps you eligible for the grant and the 20-year tariff. There is no shame in it, and often little extra cost once the lost grant is counted. Start with our DIY Solar overview to decide how much you really want to take on.

Panel tilt and azimuthSide view of a panel on a roof facing south. The tilt angle is measured from the horizontal and about 30 to 32 degrees suits Malta. A plan view shows azimuth as the compass direction the panel faces, with due south as the target.TILTSide viewNSWEPlan view: aim due south
Tilt and azimuth: roughly 30 to 32 degrees, facing due south, suits Malta.

See the grants you could claim

A professionally-commissioned system unlocks REWS grants and the 20-year feed-in tariff. See what is on offer.